Estimate #1001

Kitchen Remodel

Estimate No. 1001
Prepared Date October 17, 2026
Expiration Date November 16, 2026

Prepared By

Your Company

Prepared For

Your Client

123 Street Name, Ste 987

Sampletown, XY 50001

Scope

A full remodel of the kitchen in its existing layout: new cabinets, quartz countertops, backsplash, luxury vinyl plank flooring, recessed and pendant lighting, and paint, with all permits, inspections, and cleanup. Appliances are supplied by you and installed by us.

Description Qty Unit Price Total Price
Preparation and demolition

Floor and room protection and dust barriers

1 $850.00 $850.00

Demolition of cabinets, countertops, and flooring

1 $3,200.00 $3,200.00
Framing and drywall

Framing repairs and cabinet blocking

1 $1,400.00 $1,400.00

Drywall patch, tape, and finish

1 $2,100.00 $2,100.00
Electrical

Electrical rough-in and six new circuits

1 $4,800.00 $4,800.00

Recessed lights (installed)

8 $185.00 $1,480.00
Plumbing

Plumbing rough-in and fixture setting

1 $3,600.00 $3,600.00
Cabinets and countertops

Cabinet allowance (supply)

1 $18,000.00 $18,000.00

Cabinet installation and hardware

1 $3,400.00 $3,400.00

Countertop allowance (quartz, fabricated and installed)

1 $7,500.00 $7,500.00
Tile and flooring

Backsplash tile allowance (materials)

1 $900.00 $900.00

Backsplash tile installation (sq ft)

45 $28.00 $1,260.00

Luxury vinyl plank flooring, installed (sq ft)

220 $11.00 $2,420.00
Fixtures and finishes

Fixture allowance (sink, faucet, pendants)

1 $2,200.00 $2,200.00

Paint, walls and ceiling

1 $1,900.00 $1,900.00

Appliance installation (owner supplied)

1 $650.00 $650.00
Permits and closeout

Building permit and inspections

1 $1,200.00 $1,200.00

Dumpster, final cleanup, and haul-off

1 $1,350.00 $1,350.00

Project management and supervision

1 $4,290.00 $4,290.00
Total Due USD $62,500.00

Estimate Notes

This estimate is valid for 30 days. Allowances are budgets for your selections. If a selection costs more, the difference plus 10% is added by change order before ordering, and if it costs less, the difference is credited to you.

Not included: appliances, work outside the kitchen, removal of asbestos, lead paint, or mold if found, and any electrical service panel upgrade the utility or inspector requires. We’ll confirm the scope, schedule, and payments in a proposal and contract.